Case Studies

OPF2 Tails Line COS Bypass Construction

FMG’s Christmas Creek Mine required a 350m section of HDPE lined steel. The mine’s current OPF2 Tails Line was covered by the Coarse Ore Stockpile (COS) and the condition of this section of pipe was unknown.

If the pipe failed, an extended (and costly) unplanned OPF shutdown was likely. To cut downtime, the section of the pipe underneath the COS was to be replaced with recycled pipe from the decommissioned Windich Tails Line.

The scope of works included:

  • Construction of a new pipeline corridor in the OPF Area
  • Recovery of the decommissioned pipeline
  • Construction of the new 350m HDPE lined steel pipeline
  • Bolt up the existing pipeline
  • Tie-in 2 into existing pipeline under OPF shutdown
  • Tie-in 1, Locate and uncover existing 40 meters of Pipeline remove and replace with a new pipeline
  • Commission and hydro test pipeline

We’re proud to say that the project went like clockwork, and FMG successfully avoided any unplanned shutdowns.

$680K

Client

FMG

Location

Pilbara, WA

Project Duration

1 Month

Project Start

March 2020

Project Finish

April 2020

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Supply and Install FRÄNKISCHE Infiltration Storage System

The City of Cockburn required a section of their stormwater drainage to be upgraded to ensure the ongoing o

PathLearn more
Hayman 15 Sumping

TCD were engaged by FMG to prepare the HAY15 area for upcoming mining operations.  This involved the const

PathLearn more
Far West Hub Project

TCD were engaged by FMG for the Far Web Hub Project – Detailed Earthworks and the Supply and Construction

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us