TCD were engaged by FMG to construct a 1.8ML Turkeys Nest for the GNH Railway Overpass Project, in what was a complex yet straightforward project for our team

The project required earthworks for the construction of the Turkeys Nest, including clearing, borrow pit management and cut to fill. There was also the supply and installation of the bidim and geofabric, HDPE liner, fencing, life buoys and egress netting. As well as the supply and installation of pipework, inclusive of all flanges and valves and the 2.5km of HDPE pipe. Not to mention the commissioning and testing of the HDPE pipe and valves.

Needless to say, our team completed the project without incident, on time and on budget.

$872K

Client

FMG

Location

Pilbara, WA

Project Duration

2 Months

Project Start

June 2019

Project Finish

August 2019

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the

PathLearn more
Solomon Stockyards 1A TN Pump Install & Tie-Ins

FMG undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip an

PathLearn more
Roy Hill ROM4 Drainage

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project.  The scope

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us