When TCD Civil Construction was the contract for the preliminary site works and installation of a Type 10 Pump Station in Baldivis, it called for the a truly multi-disciplinary approach. There was a long list of requirements:

  • Clearing of the pressure main pipe routes
  • Excavation and associated earthworks
  • Installation of the type 10 wastewater pumping station
  • Thirteen overflow storage tanks
  • Associated access chamber inlet gravity sewer pipeline and site works
  • Supply, delivery and installation of all pipes, valves, fittings and pits
  • Backfilling and compaction of excavated trenches
  • Pipelines pressure testing and disinfection
  • Restoration work at inter-connections with existing water mains
  • Restoration of the site and disposal of surplus excavated material

Thanks to the seamless integration and management of our services, our team successfully completed this complex project to a high standard, on time and on budget.

$1.4M

Client

Perron Developments

Location

Baldivis, WA

Project Duration

4 Months

Project Start

July 2017

Project Finish

November 2017

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Supply and Install FRÄNKISCHE Infiltration Storage System

The City of Cockburn required a section of their stormwater drainage to be upgraded to ensure the ongoing o

PathLearn more
Hayman 15 Sumping

TCD were engaged by FMG to prepare the HAY15 area for upcoming mining operations.  This involved the const

PathLearn more
Far West Hub Project

TCD were engaged by FMG for the Far Web Hub Project – Detailed Earthworks and the Supply and Construction

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us